Lathrup Village proposed work for the week of 09/05/2022:
ASI will not work on 9/3/2022 or 9/5/2022
Roads
Week of 08/29 update
Saratoga – ASI is scheduled to place the 1st lift of asphalt on Friday (09/02).
San Rosa – Asphalt driveways were installed along with clean-up and grading. Landscape restoration is scheduled for Friday (09/02)
Wiltshire –Asphalt driveways were installed and landscape restoration should be complete by the end of the week.
California Dr SE – The 10” of aggregate base installation and finish graded. The 1st lift of asphalt was placed on Thursday (09/01).
Lathrup Blvd – Landscape restoration was completed and some punch list items.
Rainbow Court, Eldorado, Meadowbrook Way, East Cambridge – Some punch list items are scheduled for Friday (09/02).
LaCrosse - Sawcutting for driveway removals is scheduled for late in the week.
Cambridge (Bloomfield to Santa Barbara) – Sawcutting for driveway removals were completed.
Week of 09/05
Saratoga –Concrete driveway replacement is scheduled later in the week.
San Rosa – Fine grading, topsoil, and hydroseed is scheduled later in the week.
Wiltshire – ASI is scheduled to place top lift of asphalt on Wednesday (09/07).
California Dr SE - Concrete driveway replacement is scheduled later in the week.
Lathrup Boulevard – Concrete driveway repairs are scheduled later in the week.
Rainbow Court, Eldorado, Meadowbrook Way, East Cambridge –No work is planned this week.
LaCrosse – Driveway and culvert removals are scheduled to start on Thursday (09/08). Milling off the asphalt is tentatively scheduled for Saturday (09/10).
Cambridge (Bloomfield to Santa Barbara) – Driveway and culvert removals are scheduled to start on Tuesday (09/06). Milling off the asphalt is tentatively scheduled for Saturday (09/10).
Bloomfield – Driveway and culvert removals are scheduled to start on Thursday (09/08). Milling off the asphalt is tentatively scheduled for Saturday (09/10).
Lead and Copper Exterior Excavation
Week of 08/29 update – Sunde Services will complete around 5 excavations. At total of 239 excavations have been completed.
Week of 09/05– Sunde Services will continue exterior excavations.
Hydrants
Week of 08/29 update – Sunde Services did not install any new hydrants and are awaiting materials.
Week of 09/05– Sunde Services is scheduled to install 2 hydrants when they are delivered. Currently back ordered 2 – 4 months.
Gate Valves
Week of 08/29 update – Sunde Services did not refurbish or replace any gate valves. Waiting on cleaning out the gate wells.
Week of 09/05– Sunde Services will continue gate valve refurbishment after the gate wells are cleaned.
Sidewalks
Week of 8/29 update – KD Cement has continued work on the year 2 sidewalk project should be substantially complete by Friday (09/02).
Week of 09/05– KD Cement will work on the punch list for both the year 1 and year 2 projects.
Cured-In-Place-Pipe Installation
Week of 08/29 update – DVM Utilities has completed the majority of the pre-cleaning and televising of sewers to be lined.
Week of 09/05– DVM will be on hold until the liners are delivered with installation scheduled to start the week of September 12th.
Manhole Installations (In support for the CIPP installation)
Week of 08/29 update – Sunde did not install any manholes.
Week of 09/05– Sunde is scheduled to install 3 new manholes which will complete this work.
|