Lathrup Village proposed work for the week of 09/26/2022:
Roads
Week of 09/19 update
Saratoga – Saratoga was scheduled to be topped with asphalt on 09/22 but was delayed due to the rain and is being rescheduled.
San Rosa –No work was performed.
Wiltshire – Wiltshire was scheduled to be topped with asphalt on 09/22 but was delayed due to the rain. The section from Lathrup Blvd to the dead end was topped on Thursday (09/22).
California Dr SE – The undercut south of Sunset was based in with asphalt and the 2nd lift of asphalt was placed in the RCOC right-of-way.
Lathrup Blvd – Very little punch list work items were performed this week.
Rainbow Court, Eldorado, Meadowbrook Way, East Cambridge – No work was performed.
LaCrosse – The existing aggregate base material was in good condition and passed the proof roll. A thin lift of new aggregate was installed to meet grade. The 1st lift of asphalt was placed on Thursday (09/22).
Cambridge (Bloomfield to Santa Barbara) – The existing aggregate base material was in good condition and passed the proof roll. The 1st lift of asphalt was placed on Wednesday (09/21) and Thursday (09/22).
Bloomfield – The 1st lift of asphalt was placed on Wednesday (09/21) and Thursday (09/22).
Week of 09/26
Saratoga – The top lift of asphalt is tentatively scheduled for Monday (9/26) with landscape restoration scheduled for mid-week.
San Rosa – Landscape restoration is scheduled for this week.
Wiltshire – The top lift of asphalt is tentatively scheduled for Monday (9/26) for the section between Southfield Road and Lathrup Blvd.
California Dr SE – The top lift of asphalt is scheduled for Tuesday (09/27) with landscape restoration scheduled for mid-week.
Lathrup Boulevard – Minor punch list work items are scheduled.
Rainbow Court, Eldorado, Meadowbrook Way, East Cambridge –No work is planned this week.
LaCrosse – Concrete driveway repairs are tentatively scheduled to start on Thursday (09/29).
Cambridge (Bloomfield to Santa Barbara) – Concrete driveway repairs are tentatively scheduled to start on Thursday (09/29).
Bloomfield – Concrete driveway repairs are tentatively scheduled to start on Thursday (09/29).
Lead and Copper Exterior Excavation
Week of 09/19 update – Sunde Services did not complete any excavations. At total of 239 excavations have been completed.
Week of 09/26– Sunde Services will continue exterior excavations.
Lead and Copper Water Service Replacement
Week of 09/26– D’Angelo Brothers is scheduled to replace 4 or 5 lead water services at various locations throughout the City.
Hydrants
Week of 09/19 update – Sunde Services did not install any new hydrants and are awaiting materials.
Week of 09/26 – Sunde Services is scheduled to install 2 hydrants when they are delivered. Currently back ordered 2 – 4 months.
Gate Valves
Week of 09/19 update – Sunde Services refurbished 2 gate valves. Waiting on cleaning out 31 gate wells.
Week of 09/26 – Sunde Services will continue gate valve refurbishment after the gate wells are cleaned.
Sidewalks
Week of 09/19 update – KD Cement is scheduled to complete the punch list.
Week of 09/26 – The punch list will be field reviewed for completion.
Cured-In-Place-Pipe Installation
Week of 09/19 update – DVM Utilities installed 8 liners at various locations.
Week of 09/26 – DVM is scheduled to continue lining 8 – 10 sewer sections.
Manhole Installations (In support for the CIPP installation)
Week of 09/26 – Work is complete.
Goldengate Water Main Installation (11 Mile to Eldorado)
Week of 09/19 – Tentative start date. Waiting on Miss-Dig.
Week of 09/26 – Work is complete.
Fire Flow Testing
The City is working with the Southfield Fire Department to perform fire flow tests at 15 – 20 locations throughout the City. More information will be provided once a tentative schedule is provided.
|