Innovation Building 1: Construction remains on track to be complete in Summer 2020. Structural steel and all concrete floor slabs are complete with the main roof, spray-on fireproofing and the overhead mechanical rough-in ongoing. The exterior enclosure has started and will continue through the end of the year with the interior tenant build-out work scheduled to begin in November 2019.

Public Infrastructure : Demolition of two buildings at 1430 and 1500 Indiana Avenue is complete, making way for the extension of Gent Avenue into 16 Tech. Utility installations at the new intersection of Waterway Boulevard and Gent are in progress, and site prep continues for the 16 Tech bridge with the relocation of water mains.