Room 714, Sink Fixture
Test Result: 39 ppb
Remediation Plan: Taken out of service - to be replaced
Room 608, Sink Fixture
Test Result: 13 ppb
Remediation Plan: Taken out of service - to be replaced
Team Room By 608, Sink Fixture
Test Result: 30 ppb
Remediation Plan: Taken out of service - to be replaced
Team Room By 616, Sink Fixture
Test Result: 150 ppb
Remediation Plan: Taken out of service - to be replaced
Team Room By 626, Sink Fixture
Test Result: 120 ppb
Remediation Plan: Taken out of service - to be replaced
Room 616, Sink Fixture
Test Result: 5.4 ppb
Remediation Plan: Taken out of service - to be replaced
Room 624, Sink Fixture
Test Result: 15 ppb
Remediation Plan: Taken out of service - to be replaced
|