Lyons Farm Elementary School
WEEKLY CONSTRUCTION UPDATE
April 13th, 2022
Sitework
Triangle continues with asphalt work in Scott King Rd
Grading at the 3-5 play area is progressing
Exterior
Sidewalks behind back of curbs are going in
Brick for the Reading Forest outside the Media Center is complete
Loading dock concrete paving is complete with the chiller yard stoned and upper platform ready for concrete
Brick wash on the outside is progressing
Pipe gates are installed
Interior
The "mountains" in the main entry are looking good.
Clouds in the media center are up
Center rotunda is progressing
The last of the classwork millwork is complete
Library reception desk has been delivered
Interior glass is being installed
Toilets and sinks at the group bathrooms are trimming out
Duct sock in the gym is installed
Elevator machine, rails, jacks, and cab have been delivered
Looking Ahead
SITEWORK
  • Water line flush and chlorinate
  • Complete final grading
  • Skimmer pond conversions


EXTERIOR
  • Placing Sidewalks
  • Setting basketball goals
  • Landscaping


INTERIOR
  • Complete Millwork install
  • Final Paint
  • Drop ACT tile