Dredging Updates
October 27, 2020

The next section of dredging activity will require coordinated, timely movement of boats in order to reach all slips. The marina staff will call boaters with temporary slip assignments as the dredge progresses into each area. We thank you in advance for being prepared to move with 48-hour notice.

Please, don’t hesitate to reach out with any questions.
 
Float 3: Underway.
Estimated Completion: October 31
 
Float 5-7: On deck!
Estimated Start: November 2
Floats 5/7 are split into 2 sections- first, the northern section (A) with in-water disposal. Then, the dredge will modify the pipeline route and continue dredging the southern section (B) and all remaining areas -piping material to the upland disposal site.

Float 9, 11, 17, 19, 21
Estimated Start: tbd

Float 6, 8, 10, 12, 14, 16: complete!


To date, the contractor has removed over 50,000 cubic yards of material from the boat basin floor since September 21st, 2020. Thank you for your continued cooperation with the Westport Marina Phase 3 Dredging Project.

We sincerely appreciate your patience and cooperation with this project. We recognize this is a busy time of year and intend to make every effort to mitigate any potential impacts.

We will provide work plan updates and impacted areas via:

Please don’t ever hesitate to reach out for additional information. Thank You!