Dredging Updates
December 1st, 2020

We have reached the home stretch of the Westport Marina dredging project. To date, the contractor has removed over 86,000 cubic yards of material from the boat basin floor since September 21st, 2020. Thank you for your continued cooperation as we bring this critical project to completion.

The final section of dredging activity will require coordinated, timely movement of boats in order to reach all slips. The marina staff will call boaters with temporary slip assignments as the dredge progresses into each area. We thank you in advance for being prepared to move with 48-hour notice.
If you fail to move in a timely manner you are responsible for all costs associated with port staff or hired tug relocating your vessel.

Please reach out to the marina office with any questions.
Float 3, 5, 6, 7, 8, 9, 10, 11, 12, 14, 16: complete
 
Float 15/17A: Underway.
 
Float 17/ 19: On deck!
Estimated Start: December 3
 
Float 19/21:
Estimated Start: December 8

Float 21:
Estimated Start: December 14


Feel free to contact the marina office with any questions. The dredge operator is operating on VHF Chanel 69.

Thank you!

We sincerely appreciate your patience and cooperation with this project. We recognize this is a busy time of year and intend to make every effort to mitigate any potential impacts.

We will provide work plan updates and impacted areas via:

Please don’t ever hesitate to reach out for additional information. Thank You!