Greetings Bradley Beach-
A great week of weather... finally!
We’ll keep the focus on 3 Infrastructure projects going on at the same time and we will continue to provide updates so that you can stay informed.
Project #1 Beachfront
Outfall Pipe on Ocean Park/ McCabe Avenue beaches. Progress continues through week 4. Mobilization and sheeting has been completed. Dewatering, excavation, and removal of the existing pipe will continue through next week. Following this, new pipe installation will begin. The final steps are removal of the sheeting, clean up and demobilization. All activities are weather dependent and subject to material deliveries being on time. So far- so good! On schedule and no surprises.
|