|
Central Regional Wastewater System
The board approved an engineering services agreement with Hazen and Sawyer, and Wade Trim, Inc., for work on the Little Bear Creek Interceptor, Segments BC_10 and BC_15. The project will evaluate and improve about 17,600 feet of 12- to 21-inch clay and PVC pipe. It also includes rehab or replacement of four meter stations serving Grapevine, Colleyville, and Bedford.
The board approved an engineering services agreement with Jacobs Engineering Group for preliminary design work on Phase IV Solids Management Improvements. The project will add solids treatment capacity and redundancy to meet projected demand through 2070. Plans include two more thermal hydrolysis units, a fifth digester, and improved dewatering.
Denton Creek Regional Wastewater System
The board adopted Resolution No. R-1689 to execute the Ninth Supplemental Contract, adding Furst Ranch Municipal Utility District No. 1 as a customer.
The board also approved a contract amendment with Black & Veatch for the 5.0 million gallon per day plant expansion. The added funding covers the design of a new influent pump station, expanded screening with coarse and fine screens, and services needed to use Competitive Sealed Proposals for construction.
Mountain Creek Regional Wastewater System
The board approved a first amendment to the engineering services agreement with Garver LLC for the final design of the plant expansion. The project will increase capacity from 3.0 MGD to 9.0 MGD.
Red Oak Creek Regional Wastewater System
The board approved an engineering agreement with K. Friese & Associates for the DeSoto/Glenn Heights Interceptor RBC-4 project. It will replace 9,200 feet of 10- to 15-inch clay and PVC pipe.
The board also approved a first amendment to the engineering agreement with Jacobs Engineering for the plant expansion from 6.0 MGD to 9.0 MGD.
Tarrant County Water Supply Project
The board approved an engineering services agreement with AECOM Technical Services, Inc., for work on the fourth ozone generator and pump station upgrades. The project adds capacity to treat taste and odor issues, replaces aging equipment, and updates two pump stations. The three existing ozone generators will be replaced in future phases.
Walker-Calloway Branch Outfall Trunk Sewer System
The board approved construction, engineering, and materials testing contracts for Phase 4 improvements. The project will replace or repair about 3,000 feet of 27-inch pipe in poor condition due to corrosion.
Huntsville Regional Water Supply System
The board approved an engineering agreement with Plummer Associates for the treatment plant master plan. The project will outline short- and long-term upgrades needed to meet demand through 2075.
|