Preparation for paving on Albany Avenue will continue next week.
Central Hudson: Lucas Ave main installation will continue next week.
Midtown Parking Lots Green Improvements: work is proceeding on the Prince Street lot (next to Moneky Joe). Cornell lot curbing is expected to arrive next week. After curb installation, work to finish paving, landscaping, and striping can proceed. The Cornell lot is expected to be completed by end of October.
Franklin Street Complete Streets work continues with granite curb, bluestone, and concrete sidewalk installation along the north and south side of the road from Wall Street to Broadway.
Wilbur Ave construction next week will include shoulder widening, underdrain installation and guiderail removal.
Regular Roadwork Updates are posted on the City's website here.
More info about paving projects can be found at https://kingston-ny.gov/paving.
|