Grogan’s Mill Road and South Millbend Drive
Intersection Project nears completion
Project update: Contractor Teamwork Construction Services has completed pavement work at the intersection. All dual-left-turn lanes are now open for use. The new traffic signal poles and signal heads have been installed. Over the next couple of weeks, Teamwork will be backfilling median areas, adding sod, placing final pavement markings and striping, as well as cleaning up the project site. The signal crews will continue installing wiring as well as pedestrian poles, and then remove the temporary poles and signals once the new signals are operational.
The project started at the end of September and is a 90-calendar day project.
Project Scope: This project creates additional turn-lane storage by constructing double turn lanes for traffic on:
1. Northbound Grogan’s Mill turning onto westbound South Millbend
2. Southbound Grogan’s Mill turning onto eastbound South Millbend
3. Eastbound South Millbend turning onto northbound Grogan’s Mill
In addition, right-turn-lane improvements were made throughout the intersection.
Signal locations have been redesigned for this project, which includes concrete median removal as well as additional pavement. The project required rerouting some intersection traffic during construction.