The Riverside County Transportation Commission (RCTC) and Metrolink have scheduled a weekend closure of the 91/Perris Valley Line on November 21 and 22, 2026, to allow crews to complete important track and station improvements as part of the Perris-South Metrolink Station and Layover Facility Project.
Metrolink train service will be suspended at the following stations:
- Riverside-Hunter Park/UCR
- Moreno Valley/March Field
- Perris-Downtown
- Perris-South
Metrolink service from Riverside-Downtown and stations west will continue to operate on the regular weekend schedule. Train service at the affected stations will resume on Monday, November 23, in time for the morning commute.
The weekend closure is needed to allow crews to safely install new track switches, replace emergency vehicle and pedestrian crossings, extend the station platform, and complete required inspections before train service resumes.
|