Next week's schedule is as follows:


Monday, August 4

  • Tree Clearing along Yellowstone Trail
  • Restoration around the project

Tuesday, August 5

  • Tree Clearing along Yellowstone Trail 
  • Paving Shorewood Oaks
  • Restoration around the project

Wednesday, August 6

  • Finish Tree Clearing along Yellowstone Trail under closed conditions
  • Prepping Yellowstone for paving
  • Tree clearing and grubbing Eureka Rd
  • Prepping Eureka Rd for paving
  • Restoration continues

Thursday, August 7

  • Paving Yellowstone, Eureka, and Orchard Circle

Friday, August 8

  • Any final restoration


Week of August 11

  • Striping Yellowstone Tr and Public Works on Thursday, August 14.
  • Any final clean up needed