Starting the week of August 11, B Street will be closed, and A Street will be open for traffic to cross Mill Street. Additionally, E Street will be closed, and D Street will be open for traffic to cross Mill Street.
We appreciate your patience and apologize for any inconvenience. Multiple crews are working concurrently and at different locations throughout Mill Street to support project progress.
Below are the additional traffic details.
Mill Street: South A Street to E Street
- Closed to traffic
- Paving in progress
- A Street will be open to cross Mill Street, along with D Street, at this time
Mill Street: E Street to Centennial Boulevard
- Closed to through traffic, open to local traffic only
- Side streets in this area will close one by one as work progresses north
- Crews are currently excavating and working on sidewalks
The schedule may vary due to unforeseen conditions, but we will do our best to update you ahead of time.
The contractor will coordinate any driveway closures directly with residents. If you have any specific questions about the schedule or your specific property location, please contact construction superintendent Dustin Davies at 971-375-3406.
|