Early morning construction work is scheduled to begin on Wednesday, July 16. Crews will start at 4:30 a.m. between Main Street and B Street, with early morning work continuing over the next three weeks toward H Street. This work will occur intermittently as needed to support project progress. You may hear construction noise during these early hours.
We appreciate your patience and apologize for any inconvenience. If you have questions or concerns, please contact the project construction superintendent or City staff.
As previously shared, you may see saw cutters working throughout the project area as crews prepare sections for excavation. For your safety, please keep a safe distance—these tools can create dust, debris, and noise during operation.
Mill Street is closed from Main Street to C Street through July 31. While work continues in this section, we will be constructing new sidewalks between E Street and H Street.
Here's the current plan:
West Side (E Street to H Street):
- Sidewalk area excavation begins this week.
- Concrete pouring is planned for the week of July 14.
East Side (E Street to H Street):
- Excavation is scheduled to begin the week of July 21.
- Sidewalk installation will follow.
The contractor will coordinate any driveway closures directly with residents. If you have any questions, please contact construction superintendent Dustin Davies at 971-375-3406.
Thank you for your continued patience throughout construction. Please see the map below for updated detour and closure information.
|