We appreciate your patience and apologize for any inconvenience. Multiple crews are working concurrently and at different locations throughout Mill Street to support project progress.
Mill Street: South A Street to E Street
- Closed to traffic
- Paving in progress
- Either A Street or B Street will be open to cross Mill Street, along with E Street, at this time
Mill Street: E Street to Centennial Boulevard
- Closed to through traffic, open to local traffic only
- Side streets in this area will close one by one as work progresses north
- Crews are currently excavating and working on sidewalks
The schedule may vary due to unforeseen conditions, but we will do our best to update you ahead of time.
As a reminder, early morning construction work began on Wednesday, July 16. Crews may start work as early as 4:30 a.m. on an intermittent basis to meet the project schedule.
The contractor will coordinate any driveway closures directly with residents. If you have any specific questions about the schedule or your specific property location, please contact construction superintendent Dustin Davies at 971-375-3406.
|