Per DOTD:
Mayor Mark,
We had a very productive on-site review of the new bridge's progress recently. The contractor is currently working on filling the concrete decks, a process that will continue over the next several days. After the concrete is poured, it will need 28 days to cure before any work can begin on the surface. In the meantime, you may notice additional work being done on the approaches and sides of the structure.
We estimate that the bridge will be completed in the late fall of this year. However, depending on the contractor's schedule, residents may start driving on the new bridge before it is officially finished. Keep in mind the fall date is an estimate. Conditions such as tropical systems could push that back to winter if days are missed, etc.
|