|
WHAT’S HAPPENING: The Mt. Vernon Avenue Bridge project is nearing completion, with the bridge set to open in late-August. As part of the remaining improvements, crews will reconstruct Kingman Street to widen it, install new pavement and add a new curb and sidewalk along the south side of the street.
Crews will reconstruct the street one half at a time and Kingman Street will be open to local traffic only. Residential access to driveways will be maintained, with some temporary restrictions when the street is paved. Access for residents on Kingman Street will be maintained via Cabrera Avenue.
WHEN: Street reconstruction will begin as early as Monday, July 28 and will take approximately three weeks to complete. Construction activity will take place weekdays, Mondays through Fridays from 7:00 a.m. to 5:00 p.m.
WORK SCHEDULE:
-
Weeks of July 28 and August 4 – Crews will work along the south side of Kingman, including demolition, grading, street widening, curb installation, sidewalk construction, and repaving.
-
Week of August 11 – Traffic will shift onto the newly paved south side of the street as crews reconstruct the north side. Crews will provide ramp access to residential driveways.
WHAT TO EXPECT: Large construction vehicles like compaction rollers, loaders and delivery trucks may be in the area during work hours. You may hear noise or feel vibration related to construction activity. All construction is dynamic, and this schedule is weather-permitting and subject to change.
|