Filming:
430 N Michigan Ave
On Saturday, July 5 & Sunday, July 6, a feature film produced by 2X Blind Partners, Inc. will be filming interior scenes at 430 N Michigan Ave. During filming, prep and wrap, parking will be prohibited at the following locations:
- Friday, 7/4 at 11PM to Sunday, 7/6 at 10PM
- West side of Lower Michigan from Hubbard to Illinois
- North side of Hubbard from Wabash to Lower Michigan
- East side of Rush from Illinois to North Water
If you have any questions or concerns, please contact Patrick Muldoon (Location Manager) at 872-272-6636 or Kirby Muldoon (On-Site Coordinator) at 708-837-1642.
Street Resurfacing - Wabash Ave from Wacker Dr to Balbo Dr
Starting July 7, street resurfacing work will begin on Wabash Avenue from Wacker Drive to East Balbo Drive. The work is a part of the Chicago Department of Transportation's Arterial Street Resurfacing Project.
The work will include ADA sidewalk improvements, curb and gutter removal and replacement, milling and paving the existing asphalt, and striping improvements. During construction, temporary "No Parking" signs will be periodically installed. These temporary signs will restrict parking during working hours, while adhering to rush hour restrictions on construction closures.
Work is estimated to be completed by October 31, 2025.
Jackson Blvd Bridge Construction
CDOT will be performing work on the Jackson Blvd Bridge between 10am and 5pm on Thursday, July 10 and Friday, July 11. During the project, the Jackson Blvd Bridge will be closed to pedestrian and vehicular traffic.
Ohio Street I-90/94 Feeder Ramp Resurfacing
The Illinois Department of Transportation (IDOT) will be performing resurfacing work on the outbound lanes of the Ohio Street feeder ramp. Only two lanes will be closed at a time. The project is estimated to be in progress until late 2025.
Halsted Avenue & Chicago Avenue Bridge Project
Last week's Reilly Report outlined preliminary plans for CDOT's work on Halsted Avenue and the Chicago Avenue Bridge, set to begin August 1 and September 1 of 2025, respectively. CDOT's proposed work schedule is 7:00am-3:30pm on weekdays, with the possibility for work on Saturdays during the same working hours. To watch a recorded meeting of CDOT’s presentation of this project, please click here.
The work on Halsted Avenue is expected to be completed by the end of Summer 2026, and work on the Chicago Avenue Bridge is expected to be completed by the end of the year 2026.
676 North Michigan Avenue Façade Project
Redmond Construction was hired to complete a façade project at 676 North Michigan Avenue. Currently, the following closures are in-place:
- Sidewalk on the south side of Huron, from Michigan Avenue to a point 150' west thereof
- Curb lane on the south side of Huron, from Michigan Avenue to a point 150' west thereof is being used as a pedestrian walkway
- Partial sidewalk closure the west side of Michigan, from Huron to a point 100' south thereof
This project is expected to be completed by fall 2025.
State Street Bridge Project
Chicago Department of Transportation (CDOT) has begun structural repair work on the State Street Bridge. Throughout the project, the bridge will remain closed to vehicular and pedestrian traffic. State Street will remain open on both sides of the bridge during construction, and vehicles crossing the river will be rerouted to Clark Street and Dearborn Street.
The project is expected to be completed at the beginning of December 2025.
River North Lighting Project
The Chicago Department of Transportation (CDOT) has completed new light pole installation in the area bounded by Chicago, Ontario, Orleans, and the river. CDOT continues to restore infrastructure trenching.
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00am - 3:30pm, Monday - Friday; with the occasional extension to 5:30pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
Once the project is complete, asphalt restoration will occur in over the month of July 2025.
Bally's Casino Caisson Pours
- Caisson pours are nearing completion and will be followed by foundation and utility work
- Total number of Casino and Hotel caissons: 356
- Total Casino Piles: 202
Work hours will continue to be 8am-8pm. However, if an issue arises during a pour, there is the potential that crews will work past 8pm. Once a caisson pour begins, it cannot stop until it is finished.
|