West Cliff Update

November 2023

🚧 Construction Report 🚧


Granite Construction is completing excavation work on sites 920, 1016, and 932 West Cliff.

Check out the behind-the-scenes action in our latest video!


What is happening now?

  • The team is reaching bedrock to support new infill walls, a crucial part of the West Cliff Stabilization project initiated in response to the 2023 January storms.
  • Concrete work kicked off on November 9th and will continue in the upcoming weeks.


Weather Challenges

  • Project sites are in challenging locations, with weather and changing ocean conditions influencing the timeline.
  • Completion target: end of the year.


Extended Work Hours

  • Granite Construction is authorized to extend weekday hours, some nights, and Saturdays to meet the aggressive project timeline.
  • Early starts possible: Crews may commence work as early as 5 a.m. on Monday, November 13th, and Wednesday, November 15th.


We'll keep you posted as the project progresses, so stay tuned for more updates! 

Thanks for joining our community meeting on November 7th!


Watch the Webinar Recording Now!

Save the Date


Next community meeting:


🗓️ Date: December 5, 2023


🕠 Time: 5:30 PM - 7:00 PM



🏢 Location: London Nelson Community Center

Learn more about the project that is underway!

Stay up to date!