Intermittent daytime pile driving for the second half of the new Georgetown Pike Bridge is planned to begin January 22 and continue through mid-March. Pile driving will occur Monday through Saturday and is necessary to construct temporary retaining walls that will enable excavation for bridge foundations.
What to Expect:
When work is active, neighbors will hear hammer strikes every few seconds.
The 495 NEXT team appreciates the community’s understanding as this impactful work progresses.
Resources:
View features of the 495 NEXT project near your property by using the interactive map on 495NEXT.vdot.virginia.gov.
Check 495NEXT.vdot.virginia.govfor the latest construction updates and to sign up to receive the project newsletter and other information.
Construction plans are subject to change due to weather, utility relocations performed by outside companies, resequencing of work to facilitate on-time completion of the overall project, and other factors.