COMMUNITY UPDATE

Greetings,


The Association has received the following update from Frontier regarding upcoming work in the community. We are sharing this information to ensure all residents are informed and aware of the planned activity.


Dear Inspiration Community Residents,


Frontier is excited to share that the Phase 1 of Frontier’s six phase fiber installation work in the community is expected to begin on or about Monday, May 19, 2025. The work will be performed by Frontier Communications and Future Infrastructure, LLC crews.

When construction is complete, Frontier’s reliable, award-winning, 100% fiber-optic service will be available throughout most of the Inspiration Residential Association.Fiber Internet is lighting fast so it can handle multi-gig speeds of today, tomorrow, and the future. Nothing will ever be faster. For more information about Frontier’s products and services, including special pricing for new customers and additional services like YouTubeTV and Netflix, visit www.frontier.com/shop.


Frontier and Future Infrastructure will be distributing door hangers to the affected homes on or about Thursday, May 15, 2025. These door hangers will provide an overview of what to expect during construction and a contact number should you have any questions about the work in your area. Key contact information is also provided below.


Phase 1 is expected to include work within Collin County Water Control &

Improvement District #3's, (“the District's”) authorized right of way areas along the following streets:

Believer Lane

Huffines Boulevard

Promise Lane

Eden Edge

Paradise Lane

Sapphire Lane

Felicity Place

Pearly Way

Valor Way

Fiber services are expected to be available in the following villages this SUMMER:

Destiny

Harmony

Paradise

Discovery

Hope

Success

Faith

Inspiration Point

Wisdom

Grace



Planning for Peace Village and Unity Village work is in process and more information will be available soon.


Please note that crews will be onsite weekdays from 7 am - 6 pm and their work will be confined to the District's street right of way and/or existing utility easements in front yards only. Any and all damages (district/resident/business) should be reported immediately to the onsite supervisor on duty for Future Infrastructure, LLC directly at 469-978-4984 or NMallory@prim.com. If your complaints to the on-site supervisor are not handled in a timely manner, they may be escalated to the General Manager for the District, Greg Wilkerson, at GWilkerson@ccwcid3.org. For questions about the status of the current or future construction plans for specific villages, please contact Frontier Communications at 469-995-2550 or FTRQACentral@ftr.com.


Thank you for your patience during the fiber construction work. Frontier looks forward to providing you with an unparalleled fiber-optic internet service!

Phase 1

Faith & Harmony Villages

May 18 - June 6

Phase 2

Grace Village

June 2 - June 20

Phase 3

Paradise Village

June 9 - June 27

Phase 4

Wisdom & Inspiration Point Villages

June 23 - July 11

Phase 5

Destiny, Discovery & Hope Villages

June 30 - July 18

Phase 6

Success Village

July 14 - July 25

Sincerely,

Ryan O'Neill

Frontier Communications Director Construction & Engineering, Texas

ryan.oneill@ftr.com | 940-765-1187

Heather Bordner-Ayyob
Community Manager

Samantha Howse

Lifestyle Director

showse@ccmcnet.com

Community Standards Coordinator
Anna Wood


Member Service Coordinator

Brittney Nelson

brnelson@ccmcnet.com


Club Inspiration
1715 Inspiration Blvd.


Office Hours 8 am - 5 pm
Monday - Friday
Office Hours: 10 am - 2 pm
Saturday
Inspiration Residential HOA is proudly and professionally managed by
469-522-2120
After Hours HOA Emergency Number
1-800-274-3165