Turner’s Fourth Quarter Building Cost Index
In the 4th Quarter of 2022, the Turner Building Cost Index increased to a new high of 1332. This is a 1.6% quarterly increase from the Third Quarter and an 8.29% annual increase from the Fourth Quarter of 2021.
Turner says transportation costs are stabilizing as are material costs such as steel, lumber and aluminum. They also see skilled labor shortages in regions with stronger construction activity. Let’s explore these factors further:
Transportation Costs
Rates have dropped significantly, although some shipping lanes prices are still much higher priced than they were pre-pandemic.
Climbing oil prices translate directly to higher diesel prices. U.S. diesel prices are up significantly from last year and likely to go higher. These costs could be passed down to shippers, making international shipping even more expensive. Trucking logjams are reported throughout Europe.
Rail disputes are a problem, with a threatened strike leading the U.S. government to pass a law upholding a settlement reached in September between unions and rail companies. Ground transport instability causes fluctuations in transit time for imported and exported goods, although transit times have continuously fallen this year.
Wondering when we can expect freight rates and shipping prices to level off? The answer is not yet. Freight forwarders do their best to move goods on schedule without additional fees, but in this unstable period, delays and additional charges can still arise. The logistics of transporting materials will likely remain challenging due to driver shortages, especially for construction sites in more remote areas of the country.
Material Prices
Though the supply chain remains volatile, 2022 brought some signs to indicate we’re heading in the right direction, albeit slowly. Many materials have stabilized in terms of pricing, but we anticipate seeing continued upward pressure on some material prices because demand is still strong. However, as kinks in the supply chain begin working themselves out, it will help tap some of those prices down a bit. As prices stabilize, we expect year-to-year inflation to settle. In 2023 we should plan for overall escalation of around 6%.
Labor shortages have a significant effect on construction material cost and availability. A supplier might have access to raw materials, but lack labor to process and transport them. Workforce shortages will continue to affect different levels of the supply chain, from collecting and processing raw materials, to production, manufacturing, and transportation.
We still see shortages of copper and mechanical/electrical equipment, but aluminum, semiconductors, lumber and roofing materials are stabilizing at current levels. Russia is a heavy copper producer and Ukraine is a major exporter of metals and other raw materials. War in Ukraine created supply barriers and triggered increases in the export prices of materials like copper and aluminum. As this war continues, we can expect continued shortages and price increases for these and other commodities.
The popularity of alternative materials has caused prices of products like steel to trend down in an effort to sell more product. Steel looks better in price and availability now but even with the reduced cost per ton for structural shapes prices will remain higher than what they were.
There are indications of a copper shortage, which could cause prices to go up in 2023. Copper’s volatility stems from multiple factors; not just war in Ukraine, but also instability in China. Aluminum remains a high-demand commodity but is showing signs of stabilization.
Strong demand stemming back to 2020 caused semiconductor and material shortages that heavily impact lead times on generators, switch gear, and other electrical components. Expanded production and efforts to restore semiconductor manufacturing should help stabilize supplies for 2023, but it will take longer to fully recover.
Lead times for many mechanical and electrical products are still several months to a year or longer out. These challenges will continue into 2023. Custom mechanical equipment has over a year lead time right now. In some cases, this is longer than it takes to build an entire building. 2MW generators have an 80-week lead time. It’s likely to get worse before it gets better.
Lumber is under control, and we don’t expect price hikes unless hurricanes affect supply levels and pricing due to rebuilding demand after their passing.
Prefabrication continues to be an option in the commercial construction market. Using prefabricated interior and exterior wall panels helps complete time-sensitive projects on schedule.
Skilled Labor Shortages
The construction industry needs to attract 546,000 additional workers on top of the normal pace of hiring in 2023 to meet labor demand according to Associated Builders and Contractors (ABC).
Contractors continue to experience substantial demand from a growing number of projects associated with chip manufacturing plants, clean energy facilities and infrastructure. Also, too few younger workers are entering the skilled trades, creating not only a construction labor shortage but also a skills shortage.
There is an acute shortage of workers in almost every sector of the economy, caused partly by the pandemic-induced “Great Resignation” and the mass retirement of the Baby Boomer generation. With labor force participation at all-time lows and a recently booming construction industry, we may continue to see a large deficit of capable construction workers, especially those in the skilled trades, for some time to come.
Outlook
Forecasting tools are critical because there’s often a distinct difference between what an owner thinks something should cost, and what it will actually cost. Risk Analysis allow us to plug in decades of escalation data and consolidate that information into intuitive reports. Then we can share that data with the project team and our clients to help make informed decisions on the most likely construction project pricing and escalation levels.
|