Here is the latest forecast and how recent price fluctuations may affect your projects. Also, read about our true Halloween experience, below.
The main reason construction economists explain cost increases on Industrial Construction projects is the effect on direct and in-direct field construction labor caused by delays initiated by wearing PP all day, smaller crews, social distancing, cleaning routines, busing and site check in routines.
The cost impact on a $25 million Industrial (200,000 man-hours) project could be in the 5% to 7% range, without taking into account the significant spike in construction materials.
This is less the case with Commercial / Residential construction, economists anticipate that this construction category will experience minimal change in productivity, however these facilities will still be impacted by skyrocketing construction materials costs.
Increased construction materials prices is a major concern, brought on by pent up demand after the Covid slowdown and the current USA housing boom.
Concrete (Ready Mix) + 5% in the last 12 weeks.
Rebar + 15% to 45% in the last 4 months.
Formwork + 15% to 22% in the last 12 weeks.
Bricks / Concrete Blocks + 7% in the last 15 weeks.
Lumber / Plywood / OBS + 85% in last 3 months, we are seeing some prices starting to trend downwards now.
Pipe & Fittings (CS / SS) + 15% to 20% in the last 3 months.
PVC Pipe & Fittings + 4% in the last 8 weeks.
Copper materials / Electrical cable + 10% in the last 4 months.