LEAD has surveyed businesses across North Carolina every two years since 2014 on behalf of the state’s NCWorks Commission, with a particular emphasis on hiring challenges, recruitment and retention, and other business needs. We recently published a report as well as an interactive dashboard displaying the results of the most recent survey, carried out in the winter of 2023 and early 2024. The survey found that the percentage of businesses reporting hiring difficulties has fallen from 81 percent of employers who tried to hire in 2021to 62 percent of employers in 2023, a level closer to the pre-pandemic level of 56 percent.
Since 2014, the number of jobseekers per job opening in the state has generally declined, making it harder for employers to find talent while generally providing more opportunity for jobseekers to find a job. In the past year this ratio has crept back up as the labor market has weakened, perhaps explaining why employers are not having as much trouble as they did following the beginning of the Covid-19 pandemic. While longer-term demographic trends may keep this ratio lower than it has been in the past, a future recession could also push this ratio higher as large numbers of unemployed individuals seeking a dwindling number of open positions.
Construction has been slow going for the past several weeks due to the rain leaving us with muddy conditions, however, we have a big hurdle completed with AT&T relocating lines last week, which has caused several delays out of our control.
Recent work completed:
Concrete sidewalk has been completed on both sides of Locust.
Contractor has been installing silva cells and bio-cells along the south side.
Utility subcontractor has been onsite this week working on stormwater in the Maple Street intersection area. This has taken an extended period of time due to locating the old underground utilities.
The contractor is working today to move fencing on the east side of Locust down 7th to Maple into new locations.
AT&T has relocated lines to new poles with current lines. AT&T will be replacing lines with small fiber lines, which will be located directly under the Duke lines and not at the lower height they currently are located.
Upcoming work:
Duke Power to be on site Monday 8/19/24 to remove 5 poles inside the fence.
Concrete sub should be installing C&G in areas where the silva and bio-cells have been installed.
Electrical contractor will be installing conduit for lights and other items on the south side.
Utility sub to continue to install stormwater and sanitary sewer in the Maple Street intersection area. When this is completed, an updated schedule for the Maple Street intersection reopening will be available.
Coordination, material gathering, and installation work continues on the pedestrian signal relocation at the N. Grove intersection.
After utility poles are removed, we anticipate an updated time frame for the Maple Street intersection