November 2026 News

The East County Advanced Water Purification Program is making exciting progress this fall across the various project sites. Active construction is underway in Santee, the City of San Diego and Lakeside.

The Education Center on Fanita Parkway in Santee is approximately 95% complete, with the recent pouring of the interior flooring marking a significant construction milestone. Planning and development of the educational exhibits inside the building are also in full swing. If you’re interested in signing up for our tour program interest list click here.

 

Outside the building, construction crews are making progress on sitework, including curbs and sidewalks. Final paving is among the remaining tasks before the site can be fully occupied by staff.

 

Before the end of the year, crews are expected to complete the last pipeline connection to the East County AWP campus, followed by start-up and commissioning.

What's Happening at the Dechlorination Facility?

Check out these new aerial views of the Dechlorination Facility in Lakeside, where mechanical and electrical work is underway. 


Purified water from the East County AWP Facility in Santee will travel approximately 10 miles to the Dechlorination Facility where chlorine will be removed before entering Lake Jennings. This process will protect fish and aquatic plants in the lake. 


While similar reservoir augmentation projects exist in states such as Virginia, Georgia and Texas, East County AWP is one of California’s first permitted indirect potable reuse projects set to use surface water augmentation. Explore this map to see where potable water reuse is happening around the globe.

East Mission Gorge Pump Station Nears Completion

Construction at the East Mission Gorge Pump Station, near the westbound State Route 52 onramp and Mission Gorge Road in Santee, is nearing completion.

 

One of its functions will be to transport wastewater to the East County AWP facilities. Crews are finishing work on the pumps, electrical and communications systems, along with exterior structures.

 

The next steps include restoring curbs, gutters and fencing as well as repaving. The lane closure near the onramp is expected to be opened back up before the end of the year. All traffic impacts are posted and updated regularly on our online interactive construction map. 

Temporary Sewer Odors During East Mission Gorge Pump Station Construction

As part of the project, crews are constructing a new sewer diversion structure and rehabilitating the existing sewer force main. The temporary bypass pumping system (above) is being used to keep wastewater flowing while this work is underway.


During wet weather, sewer flows increase and bypass pumps at the East Mission Gorge Pump Station are used to move wastewater through the sewer force main.


These activities may cause temporary odors in the area, particularly during wet weather. Construction at the pump station and removal of the temporary bypass pumping system are expected to be completed by the end of the year. A permanent odor control system is also being installed for long-term operation of the pump station.

The white structures on site are the permanent odor control system.

Microtunneling Planned Beneath State Route 52

Microtunneling is planned beneath State Route 52. This work will connect Mission Gorge Road pipeline construction to the East Mission Gorge Pump Station.


This trenchless construction method will be used to install a 60-inch steel casing beneath State Route 52 without disrupting highway traffic. The casing will house three pipelines that will transport treatment residuals to the City of San Diego’s sewer system, redirect excess wastewater flows during wet weather and convey wastewater from Padre Dam’s service area to the East Mission Gorge Pump Station.

 

The process involves excavating a launching and receiving pit and using a specialized boring machine, together with a hydraulic pipe jacking system to excavate soil and install pipe sections simultaneously. Microtunneling construction is anticipated to begin in spring 2027, pending a Caltrans permit, and is expected to last approximately six to seven months.


Temporary lane closures on Mission Gorge Road are expected during construction, and updates will be posted on our website, social media and online interactive construction map.

Mission Gorge Road Pipeline Work Nearly 75% Complete

Construction along Mission Gorge Road in Santee and San Diego, including work within Mission Trails Regional Park and nearby streets, is nearly 75% complete. The work includes rehabilitating an existing sewer pipeline and installing a new East County residuals pipeline in partnership with the City of San Diego.

 

Once work is complete along the westbound lanes of Mission Gorge Road in Santee, construction will shift to the eastbound lanes. This next phase will include the installation of a new Padre Dam sewer force main that will run from the Meadowbrook Mobile Home Park to the East Mission Gorge Pump Station via Mission Gorge Road and the microtunneling segment under State Route 52. The pipeline will divert wastewater from part of Padre Dam’s service area through the East Mission Gorge Pump Station to the East County AWP facilities for treatment. Currently, this wastewater is discharged directly into the City of San Diego’s sewer system.


This work is expected to begin in the spring of 2027 and end in late summer of 2027. Stay tuned for updates. 

 Reminder: Aboveground Pipeline Within Mission Trails Regional Park is Temporary

We’ve received questions about whether the aboveground pipeline that runs 4 miles along Father Junipero Serra Trail within Mission Trails Regional Park and along a portion of Mission Gorge Road is permanent. 


No, the pipeline is temporary and is planned to be removed in sections throughout this winter season. 


It serves as a bypass to keep wastewater flowing during peak wet weather events while crews complete underground sewer pipeline construction. This allows crews to work on the underground pipeline without having to repeatedly connect and disconnect the existing pipeline, therefore helping speed up the construction timeline.

Final Construction Activities Underway

on Mast Boulevard

We appreciate your continued patience while final construction activities are underway along Mast Boulevard in Santee. While contractors have wrapped up the primary construction work, a few final punch-list items remain. This includes minor adjustments to system control valves and valve box lids, which will result in intermittent temporary lane closures.

 

Additionally, through mid-December of this year, the purified water pipeline will undergo fill up and draining activities to verify that the pipeline is certified for East County AWP operations. This will require intermittent traffic control to access valves. This is a standard procedure to commission water pipelines.


All remaining work is expected to be completed by spring 2027.

Thank You for Celebrating Halloween With Us!

Thank you to everyone who stopped by our booth at the 4th Annual Halloween Spooktacular at Santee Lakes on October 24! We enjoyed meeting members of our community, seeing your creative costumes and sharing information about the East County AWP Program. 

We appreciate you taking the time to visit us! 


Photo Credit: Scott Lagace

 
 

The East County Advanced Water Purification Program will create a new, local, sustainable and drought-proof water supply. The Program will use state-of- the-art technology to purify East San Diego County’s recycled water to produce up to 30 percent of the region's water needs.

Facebook  X  Instagram