P R O J E C T

U P D A T E S


Project Phases:

Our project work moves through a process that's divided into four phases: Defining, Planning, Execution and Completion. For detailed definitions of each project phase, go here

PLANNING PHASE

Solar Panel Project at CRC

Verde Solutions LLC, a solar company, completed plans for the solar array at the Community Recreation Center, and submitted them to the Village of Wilmette for permit review the week of September 16. The permit is currently pending Village approval.

EXECUTION PHASE

Gillson Park Infrastructure Project

Significant progress is being made on the lakefront project at Gillson Park. Crews have focused on asphalt milling, concrete removal, storm sewer maintenance, and laying subsurface materials for sidewalks and curbs. Weekly on-site meetings ensure timelines remain on track, and with asphalt plants operating through mid-December, there is optimism about completing key Phase One elements before winter.



The project is still slated for completion by spring 2025, prior to Memorial Day weekend. Click here to learn all about the Gillson project; click here for the Gillson FAQ document.

 

EXECUTION PHASE

Langdon Shoreline Protection Project

The work at Langdon progresses. The revetment is complete from the north property line to the haul road. The revetment on the south side of the property has continued. Ongoing deliveries of armor stone and backfilling progresses around the completed portions of the revetment. Once the revetment is complete, work on the path from the beach back to Sheridan Road will begin. Some plantings will be installed this fall and the rest will be planted in spring, based on what is best for the plant species and as construction allows.


This project is still scheduled for completion in the spring of 2025, before Memorial Day weekend. Click here to learn more about the Langdon Shoreline Protection and Beach Access project.

COMPLETION PHASE

TREE PLANTINGS

This year, the Parks and Planning Department planted 43 trees in the spring and 49 in the fall, working toward the annual goal of 50 trees per season as outlined in the district’s sustainability plan. This year’s efforts focused on smaller parks like Wheeler, Lockerbie, and Earlywine, and progress continued at larger parks such as Community Playfields. Future planting seasons will prioritize the distribution of trees across all parks while addressing invasive species removal and replacing them with native species to enhance the landscape and canopy diversity.

A D D I T I O N A L

U P D A T E S

BUDGET SEASON - Discussions and departmental presentations for the District's 2025 budgets include reports from Racquet Sports, Ice, Lakefront, Pool, and Recreation.


TRUTH IN TAXATION LAW RESOLUTION - Discussed and voted on during the meeting. Additional budget discussions included the PTELL Resolution, which will be introduced and discussed at the next Committee of the Whole meeting and voted on at the December Board meeting. On Monday, December 9, there will be a public hearing to discuss the proposed tax increase for 2024, which will take place immediately before the December Board meeting.


CAPITAL PROJECT PLANS - During the COW meeting on Monday, November 18th, the Board of Commissioners discussed proposed new policies and reviewed the five-year capital project plans proposal for the district. After a thorough examination, the list of capital projects for 2025 is nearly finalized.


SOUTH BEACH OPERATIONS - In January, the District will conduct a public input process to help determine 2025 swim season operations.

A C C E S S

To view Agendas and Minutes from past Board meetings, click here. Minutes are posted after they are approved.



Next Regular Monthly board meeting: Monday, December 9 at 7:30 p.m. in the Council Chambers of the Village Hall at 1200 Wilmette Avenue.


COMMITTEE OF THE WHOLE (COW) MEETINGS:


Wednesday, December 4 - Special COW: Annual Budget Workshop – 6:30 pm

LOCATION: Mallinckrodt Center, 1041A Ridge Road (side entrance)


Monday, December 16 - Regular monthly COW meeting scheduled a week earlier due to holidays.

LOCATION: Mallinckrodt Center, 1041A Ridge Road (side entrance)


All meetings are open to the public. Details are posted on the Upcoming Meetings page on our website.


Regular Monthly Board meetings are available to view live on Channel 6 locally for Comcast subscribers. View a live meeting online here, or view previous meeting recordings here (scroll down to "Wilmette Park District"). Please check our website often for updates.

_________________


Wilmette Board of Park Commissioners:



Kara Kosloskus

President

email


Patrick Duffy

Vice President

email


Cecilia Clarke

Commissioner

email


Allison Frazier

Commissioner

email


Julia Goebel

Commissioner

email


Patrick Lahey

Commissioner

email



Mike Murdock

Commissioner

email


Send correspondence to the entire Board of Park Commissioners at:

publiccomment@wilpark.org


View our Written Correspondence and Communications Policy here

_______________


Get the Details


View Agenda Packets for the November 4, 11 and 18 Board Meetings


Watch the November 11 Regular Board Meeting online


Read Meeting Minutes

Wilmette Park District Administration Office:

1200 Wilmette Ave. 

Wilmette, IL 60091

847/256-6100

www.wilmettepark.org


_______


See what's happening on our social sites

Facebook  Instagram