On Monday, May 17th the Ontario Superior Court of Justice ruled against provincial agencies Infrastructure Ontario (IO) and Metrolinx in their claim that the COVID-19 pandemic did not constitute an emergency under the contract for a $5.5BN Eglinton Crosstown LRT transit project. The public owners argued that the contractor was responsible for any related schedule delays, additional costs, or penalties.
The judge was particularly forceful in his condemnation of what he considered to be an effort by the province to reward contractors to "...cut corners and imperil public health and safety."
Last fall, Crosslinx Transit Solutions took IO/Metrolinx to court in an effort to declare that the pandemic was an emergency per the terms of their contract for the Eglinton Crosstown LRT.
Click
HERE to read the October 9, 2020 Link2Build story in which Crosslinx Transit Solutions is quoted as saying they took the decision to file reluctantly only "after repeated efforts to work collaboratively with Metrolinx and IO failed."
Justice Markus Koehnen found that COVID-19 does constitute an emergency under the agreement, opening the door for financial relief including compensation for cost increases and setting a later completion date.
This ruling is seen by industry as an important precedent that could have significant repercussions across the country, detering owners who may be seeking to place all responsibility for COVID-19 impacts on the contractors and sureties.
A spokesperson for the company commented to the
Toronto Star that their diligence in protecting their workforce and community added up to additional costs and delays.
Crosslinx is a consortium of Aecon, EllisDon, SNC-Lavelin, and Dragados.