- OGS Statewide Road Salt Contract Issues -
- Should you have any concerns regarding the OGS road salt contract please first reach to your contractor representative.
-
If the question is not resolved please then reach out to OGS via email (ogs.sm.sst_roadsalt@ogs.ny.gov) and explain the issue. This allows OGS to better compile a record.
OGS Statewide Salt Contract 4.11.9 Delivery Timetable
Completed delivery, at the latest, is required as follows:
- Contractor is required to deliver orders of 600 tons or less* within three (3) Business Days of Authorized User placing an order.
- Contractor will be required to deliver a minimum of 200 tons per day after the initial 600-ton delivery.
- Multiple orders placed for the same delivery site that overlap will be viewed as a single order, still subject to the overall 200 tons per day minimum delivery.
Authorized Users are advised not to place orders that exceed their maximum storage capacity.
|