PMO MEETING SUMMARY 

October 24, 2022

STATUS UPDATE

We are in P4 sprint 15.


Focuses of P4:

  • SIT Mock 1 conversions 
  • Conversion fallouts to > 90% pass 
  • Click by click test script steps 
  • Day in the life business process flow & test case identification 
  • RICEWP
  • RF Smart test transactions 


REMINDERWe are now using DEV 7. Please bookmark the link below. 

DEV 7 LINK

STAFF CHANGES

Hasheem Qureshi

has joined R2R

as an SME.


CC Rinehart has

joined OCM as a 

Training Developer/

Senior Consultant.

LEARN MORE

KEY TAKEAWAYS

CLICK HERE TO VIEW FULL

PMO MEETING RESOURCES

1.

ON-SITE UPDATES


Travel Reminder: 

  • If you are traveling to Chattanooga for the January end to end on-site, please visit the Embassy Suites booking links below to reserve your room by December 13th, 2022 to secure a room at the discounted rate.
Embassy Suites Booking Link (01/10-01/12)
Embassy Suites Booking Link (01/17-01/19)

Next on-site: 

2.

CLIFF NOTES


P3 & P4 Conversions​

  • Solid progress continues and P3 conversions are expected to be completed by EOW​. 
  • We have placed a heavy focus on suppliers and customers​ conversions. 
  • Next, we will prioritize P4 conversions based on P3 conversion status​. 


SIT Test Case Scenarios​

  • All SIT test cases will be named & numbered by EOW​.
  • We have placed a specific focus on additional / new business case scenarios. ​
  • The plan for SIT 1 is click by click test case development​. 
  • The Requirements for SIT 1 have been converted into Jira as Test Cases and these are all sprint slotted so please pay attention to which ones are slotted for which sprint. 
  • Once the Day in the Life of Business Process Flow Test Cases are documented in the Excel file on SharePoint they will be converted to Jira under the SIT 1 or SIT 2 Test plans based on what is provided in the Excel file for sprints and dates.


Service Desk Plus Ticketing System

  • Last week, we hosted an initial planning meeting and identified resources to build out the needed functionality​. 
  • We have scheduled a ticketing system design workshop on 11/03​/22. 


SOP / Training Material​ Development 

  • The current process is manual​, so we are evaluating automated capture tools like Guided Learning, UIPath Task Capture, etc.


RF Smart​

  • We are on target for the scheduled Man Rd on-site demos (11/09/22 & 11/10/22). ​


P3 E2E Questions​

  • This week, we will focus on sourcing responses to all submitted questions, validating the information and sharing it back out to the E2E attendee group. 

3.

Project Helix Garners Global Attention 👏

  • View this article about our VP of Global Transformation, Basman Alias, representing Astec & Project Helix at Oracle CloudWorld. 

4.

Human Capital Management 

  • UAT conversions are in process. UAT is tentatively scheduled to begin next Monday. 
  • Payroll Parallel 1 is in progress and defects are being resolved. Payroll Parallel 2 data conversion are in process. 
  • Ongoing integration calls continue, as integrations are at risk. We are in an iterative defect resolution cycle. 2 integrations are a Pass.
  • HCM is finalizing the web clocking station setup and orders for equipment. 
  • We are scheduling weekly SOP calls to develop and send to OCM (Organizational Change Management). 