Planned Improvements for Country Club Rd
As a follow up to their presentation at a recent PVNA board meeting, last week we received the following update from City of Tucson Transportation & Mobility regarding planned improvement projects on Country Club Blvd:
You may have noticed activity on Country Club over the past couple days. This is part of the work associated with Prop 101 Package 10. The City's Project Manager sent the following info:
It is correct that a fog seal is planned for Country Club in 2023. Attached is the page from the Prop 101 program schedule with the list of segments in Fog Seal Packages 9 and 11 and a map of each. The two packages are combined into one construction project and the contractor is planning to start crack sealing and pavement patching Monday July 10.
The work will be done in two phases:
- Phase 1 (60 calendar days) - crack sealing and asphalt patching
- Phase 2 (90 calendar days) - fog sealing and striping
- Phase 2 is not expected to start until around mid-October due to temperature requirements for application of the fog seal material.