The image on the right illustrates the parking restrictions.
The second segment will begin Tuesday, May 26 and is anticipated to be completed on June 6, 2026. The second segment involves directional drilling underneath Hawthorne Avenue from Crespi Blvd to the pump station at 81 Street. Equipment and pipe staging will occur along Hawthorne Avenue between 80–85 streets, and intersections and driveways will be temporarily blocked June 1–6 for pipe assembly and pull back. Please follow MOT plans for traffic detours.
Parking Alternatives
To assist affected residents, the City of Miami Beach is providing parking codes for Zone 26 participants to use municipal surface lots 108, 109, 110 and 111 for 24-hour parking. These codes are active now through Friday, June 5 or until further notice. Enter the code in the ParkMobile App.
Parking Code: CMBNBPW
City of Miami Beach residents may sign up for parking permits and programs by visiting the Miami Beach Parking website.
|