Forest Drive Update

Last week, the contractor completed the water main work and restored the travel lanes at the intersection of Mount Vernon Road. The contractor is currently working on underground utilities and pavement patching, starting at Mount Vernon Road and working north toward Bever Avenue. This will include removing and prepping various patches on one side of the road, pouring new patches back on Friday, May 10. Forest Drive remains open to property owners only; all other traffic is required to detour. The project is on schedule and should wrap up by this fall.