Work is moving forward on O Avenue NW between 16th Street and 18th Street.

Crews continue to work on water main installation, utilities (sanitary sewer, storm sewer), and retaining walls. Pavement has been removed up to the 16th Street intersection. Residents in this area still have access to their properties from the west (the 18th Street side).

Over the next two weeks, pavement removal will continue west to 18th Street. After pavement is removed, crews will prepare for new concrete, which includes grading and placing subbase. We expect new pavement construction will begin in the next couple of weeks. Retaining wall construction will continue, and water main installation will move west from 20th Street.

As always, please do not hesitate to reach out to us if you have any questions!