Memorial Drive Update
Bever Avenue to Mount Vernon Road
Construction work on Memorial Drive will continue to progress over the next few weeks. Retaining walls are nearly complete between Bever Avenue and Meadowbrook Drive. Crews will continue to install sidewalk and curb ramps, and depending on weather and ground conditions, will begin to place sod. Between Meadowbrook Drive and Mount Vernon Road, crews will continue to work on storm sewer installation as well as begin pavement removal. Please look for door hangers notifying residents when they should begin parking on side streets to allow street reconstruction to begin.