Weather permitting, railroad flaggers will be on site Monday, July 27, which will allow for completion of the work on 29th Street between I-380 and Center Point Road. This work includes pavement replacement adjacent to the railroad tracks, installation of storm sewer, and completion of the center median with concrete pavers. This work will take approximately 3 weeks.

Also beginning Monday, July 27 (weather pending), crews will begin placing the driveways on 29th Street between Center Point Road and Russell Drive, the final work before this section reopens. 

Next Phase
In approximately 3 weeks, 29th Street will completely re-open east and west of Center Point Road, and the intersection of Center Point Road and 29th Street will be closed for the last phase of the project, reconstructing the intersection. The intersection will be completely closed for approximately 5-6 weeks. We will continue to send you updates on access and detours as we get closer to that phase.

Current Detour Info
  • Traffic should utilize 32nd Street and Oakland Road as a detour while segments of 29th Street and Center Point Road are closed.  
  • The frontage road (Madison Street NE) for I-380 northbound traffic between 29th Street and 32nd Street is open  
  • The intersection of Center Point Road and 29th Street is open and traffic may travel in both directions to J Avenue
  • Oakland Road is open