New roadway pavement has been completed to 20th Street. Currently, work on residential driveways and sidewalks from 16th Street to 20th Street is nearly complete. After grading, sodding, and temporary pavement markings are placed, O Avenue will reopen to all traffic by November 20, if not sooner.  

Next week, the contractor will begin work on a box culvert (a drainage structure) in the south shoulder area starting at 24th Street and working west. At the same time, water main installation will resume in the north shoulder area between Highwood Drive and 24th Street. If weather allows, this work will continue through winter. During winter work, signage and barricades will be used to stagger work areas and allow traffic lanes to remain open as much as possible. 

Utility relocations continue between 24th Street and Edgewood Road. 

As always, if you have questions or concerns, please do not hesitate to contact a member of our project team.