Water main installation continues on Chandler Street, and has begun along 20th Street. During this work, access to homes is being maintained.

On Monday, June 7, crews anticipate closing the entrance to Jefferson High School off 20th Street, for full pavement reconstruction and underground utilities. While this work is underway, the pedestrian crosswalk on 20th Street at the 16th Avenue intersection will also be reconstructed to comply with ADA requirements. This work is scheduled to be completed by mid-August, before the 2021-2022 school year starts.  

After the high school entrance reopens, storm sewer and water main installation will resume on both Chandler Street and 20th Street, followed by pavement reconstruction.  

As always, if you have questions or concerns, please do not hesitate to contact a member of our project team.