Winter weather has been cooperative and underground work continues on O Avenue. Storm sewer and water services were completed recently between 20th Street and 24th Street. Water main installation is underway, heading west from 24th Street. Box culvert installation remains underway, continuing west from 26th Street.  This also includes replacing residential sanitary sewer services to homes on the south side of O Avenue. Residents will have only brief interruptions to their sanitary sewer service when new services are connected. 

If favorable weather continues, both box culvert and water main installation will continue until they reach the entrance to Nedderman Farms.  

Road closures on O Avenue will continue to move westward as work progresses. Barricades are staggered so residents can access their homes.  Please be alert for moving equipment and workers.

As always, if you have questions or concerns regarding the project, please do not hesitate to contact a member of our project team. Stay safe and healthy.