During the past week, the remaining culvert sections and culvert trench fill were placed. The Spoon Creek channel was also graded and had erosion protection placed both upstream and downstream of the culvert. 

Over the next 3-4 weeks, the subgrade and subbase for the new concrete pavement will be prepared and the new pavement will be constructed. In addition, seeding along the creek bank and other disturbed areas will occur. We expect 34th Street SE will reopen to traffic by the end of October and remaining work completed by the end of November.

As always, if you have questions or concerns regarding the project, please do not hesitate to contact a member of our project team.