Progress continues to move forward on the Johnson Avenue project. 

Utility work is complete and crews are currently working on new pavement between Shelley Lane and Wesley Drive. This section of Johnson Avenue is anticipated to re-open to traffic within approximately 5 weeks.

Johnson Ave / 1st Ave Intersection Closure

Starting Monday, April 29, the intersection of Johnson Avenue and 1st Avenue will be fully closed to traffic for approximately 3 weeks, for storm sewer work and pavement reconstruction.  

The intersections of Johnson Ave and Jacolyn Drive; and Johnson Avenue and Wiley Blvd, are currently open.

Thank you for your patience, and please let us know if we can answer any questions!