Construction will be temporarily suspended the rest of this week and next due to the weather. Crews will secure the work site and ensure access is open for plows.  Assuming the weather cooperates, we expect construction will resume the week of February 15-19.  

Box culvert installation has progressed well past 26th Street, and water main work has also extended to 26th Street. When construction resumes after the weather delay, water main on 24th Street will be installed, tested, and services will be transferred to the new water main.

Our goal is to install both the box culvert and water main to just west of 27th Street over the winter, then wait for spring weather when pavement construction can resume.

As always, if you have questions or concerns about the project, please do not hesitate to contact a member of our project team.