Hi there,
Truss now repaired, stoplogs being installed 
 
We were able to quickly secure welding services and the truss has now been repaired.

LSRCA staff have also installed the flashboards and the first of the stoplogs.

Staff will continue the usual process of installing the stoplogs. This happens in stages to ensure that the water level in the reservoir is slowly raised and adequate flow is maintained downstream of the dam.

Next steps

Please stay tuned for information on how and when community consultation will take place. We will post this information to our website and through an email to the Pefferlaw Dam mailing list.

We'll be in touch again soon,


Kristen Yemm
Director, Corporate Communications and Engagement
Lake Simcoe Region Conservation Authority
905-895-1281, ext. 315
You are receiving this email because you registered for the Pefferlaw Dam Mailing List