Project Name: Jefferson Tower Interventional Pulmonology #H195024
Owner: UAB David McCabe, P.M. [email protected]
Architect/Engineer/PM: Williams Blackstock Architects Joey Tudisco (205) 252-9811
[email protected]
Pre Bid: MANDATORY Pre-Bid Conference will be scheduled prior to the date set for
receipt of bids. It is mandatory that all pre-qualified prime contractor bidders attend
the Pre-Bid Conference.
Bid Date: 09/14/2023 2:00 PM
Additional Info: Bid Info.
Pre Qualification due 08/16/2023 by 4:00 PM
The original and two (2) flash drives with duplicates of submittals are required for
pre-qualification approval; however, email transmission copies may be transmitted to the Project Manager, David McCabe, at [email protected] and cc’d to Joey Tudisco at joey@[email protected] to expedite the review process with a hard-copy of the submittal and two flash drives to be delivered within 24 hours.
|