CONSTRUCTION ADVISORY
UPDATE
February 8, 2022

Construction is in progress to replace the eastbound and westbound bridges on Platte Avenue over Sand Creek between Wooten Road and the Powers Boulevard Interchange to improve safety.
Girder Installation repeats February 8
Due to equipment issues, the final girder set for the Platte Avenue over Sand Creek bridge project is scheduled for a second night, February 8, weather and resource dependent. 

To lessen traffic impacts, the installation will happen overnight, 8 p.m. - 5 a.m. with only the right lane of westbound Platte Avenue closed beginning at the Powers Interchange.


Traffic Impacts overnight
February 8

  • The right lane of westbound Platte Avenue will be closed overnight Tues., February 8, 8 p.m. - 5 a.m. beginning at the Powers Interchange.
  • Platte Avenue eastbound will be remain open during the girder erection / installation. 

All business access will remain open throughout construction. Motorists are advised to take alternate routes when possible. All construction activities are resource and weather dependent.
PSC Phase 2 demo
Ongoing Traffic Impacts
  • Traffic control measures are in place. Please use caution
  • Construction activity is behind barrier along the median area of bridges
  • Speeds reduced to 35 mph in the work zone
  • Bicyclists and pedestrians are reminded to seek alternate routes during construction
Background
The bridges are approaching the end of their service life (built in 1956), suffering from prior flood damage (2008) and overall degradation of the structures. The project will replace the two separate bridges with one bridge structure. The project will also add sidewalks along the north and south sides of Platte Avenue over the creek to accommodate the future Sand Creek Regional Trail under the Platte Avenue bridge.
Stay in touch
Find more information about this project: ColoradoSprings.gov/PSCBridge
Project Hotline: 719-634-5056

To receive project progress enewsletters, send an email to: PlatteSandCreekBridges@gmail.com requesting to be added to notification list.

Note: If you unsubscribe from this enewsletter, you will unsubscribe
from ALL Bachman pr project enewsletters. If you wish to no longer
receive this specific project enewsletter but want to continue receiving
other project communications that you previously expressed interest in,
please hit “reply” to this email and key in the message "REMOVE." Thank you.

Project Team
  • City of Colorado Springs Project Manager - Kevin Diekelman and Senior Engineer - Aaron Egbert
  • Engineering Consultant - Wilson & Co. Engineering
  • Construction - Lawrence Construction
  • Public Information - Bachman pr