APRIL UPDATE
At the April meeting the SBC continued to complete the administrative requirements in Module One of the MSBA process. As of April 1st, the SBC may now begin submitting the various documents to complete Module One. At the April meeting the SBC focused on reviewing the first draft of the Educational Profile Questionnaire. This document explains the district's current and proposed educational facilities, teaching methodology, grade configurations and program offerings.
CURRENT STATUS Of MSBA Steps in Module One
-
Initial Compliance Certification: This is a form for the District to sign that acknowledges the requirements of the MSBA process. Signed
-
Creating a School Building Committee: One of the first MSBA requirements is to create a School Building Committee. Medfield already created a school building committee (SBC) that has been meeting since January 2023. To comply with the MSBA's guidelines for the makeup of a school building committee, the SBC added two additional nonvoting members: a Local Chief Executive Officer (Select Board Member~ Eileen Murphy), and a Local Official Responsible for Building Maintenance (Robert Quinn). Committee formed
-
Enrollment Projection Number: The SBC must present enrollment data to the MSBA. The SBC reviewed the enrollment study completed in the spring of 2024 by FutureThink. We discussed their low, moderate, and high projection numbers for the Dale Street School. We are also studying census data, and kindergarten enrollment numbers. No decisions have been made at this time, but the SBC discussed at the February meeting what number might be best for a future building project with many members expressing support for using the higher projection number of approximately 500 students.
-
Maintenance Documents: The District is required to submit documentation about how the building(s) are maintained. The MSBA wants to ensure that a District is using best practices in maintaining facilities. There are many documents to be completed that explain Medfield's maintenance process. These documents are being created by the School's administration and maintenance facility staff. Documents currently being completed.
-
Funding Process: This is the process in which the District (Medfield) demonstrates to the MSBA that the community is ready to undertake and fund a future building project. *See separate paragraph below.
TOWN MEETING/FEASIBILITY STUDY One of the requirements in Module One is the town must successfully approve the money for a Feasibility Study. The Feasibility Study is in Module Two. At previous Town Meetings, the SBC received funds for a future Feasibility Study. We currently have 1.1 million. After discussing what Feasibility Studies are currently costing neighboring towns, the SBC decided that 1.5 million will be needed. At our annual May Town meeting there will be a Warrant Article requesting additional funds for this important next step in a future building project.
We hope to see you at the Annual Town Meeting!
(Monday, May 5th @ 7:00 P.M. @ the High School)
NEIGHBORHOOD CAPTAINS!
Neighborhood Captains held their first meeting in March, and will be meeting again in April. The meeting was full of enthusiasm and ideas for reaching out to involve and inform the community of our future Dale Street School building project. If you think this is a way that you could help the SBC, please send a brief email with your name and address to casey_sbc@medfield.net.
|