Carpentry is often the largest trade on a construction project, and the availability of qualified, skilled-labor is a critical driver of success. To address this challenge, Wallworks focuses on two key elements of project management:
- Careful coordination of the carpentry tasks
- Efficient use of labor
Coordination
“Coordination of the various carpentry tasks – such as framing, sheathing, blocking and drywall work – is one of the most important aspects of project management.”
says VP and General Manager, Justin Henzel. “When we are awarded the General Trades Package, the comprehensive scope of work allows for better manpower coordination, phasing of the work, and for managing details that are important for quality.”
Labor Efficiency
In addition to carefully coordinating the work, Wallworks looks closely at the best use of labor on each project. For a 74,000 sf rehabilitation facility in Pennsylvania with a tight schedule, Wallworks used panelized roof truss and exterior wall assemblies. By prefabricating the assemblies in a climate-controlled environment, Wallworks was able to eliminate the productivity delays associated with an on-site stick-framing process in bad weather conditions.
The prefabrication construction method allowed Wallworks to drive the project ‘from slab to roof’ in 15 weeks – saving 6 weeks of time. Portions of the building were under roof in 8 weeks, which allowed other work, such as MEP and drywall to be completed ahead of schedule.