Construction Schedule Update:
Summer 2023 to Spring 2024
- Build the 400 South eastbound bridge on I-84
Spring 2024 to Early 2025
- Shift traffic to eastbound I-84 to build the 400 South westbound bridge.
- Build new westbound lane on I-84
Early 2025 to Fall 2025
- Shift traffic on westbound I-84 while crews build the eastbound lane
- Shift traffic back to eastbound I-84 to finish the westbound lanes
Late Fall 2025
ITD will communicate with the public early next year to share more information about construction.
|