What's Happening
The contractor has scheduled a pipe pullback for tomorrow evening, May 27, 2026 beginning at approximately 7 p.m. Pipe pullback is a continuous operation that must proceed without interruption once it begins and will continue until the full length of pipe is in place.
In preparation for this work, crews will be joining the pipe sections together tonight, May 26, 2026, in front of the Miami Beach Senior High School to create the continuous length needed for installation.
A small work zone will be established on the greenspace in front of the high school. All activities have been planned to minimize disruption to the surrounding area, and the school entrance will remain fully open. Access will not be blocked during school hours tomorrow. Although all activities are planned to minimize disruption, please know that some noise may occur during these operations.
Traffic Impacts
Traffic management for this phase includes a partial westbound lane closure on 22 Street, just west of Park Ave. Additionally, select parking spaces within the work zone will be temporarily unavailable during this phase.
|