The new roundabout is completely open, as of Dec. 31.
Thanks to the diligent work and effective scheduling of our construction contractor, the road closures to build the “legs” of the roundabout were completed earlier than originally expected.
We expect to complete the remaining work by April 30. This includes:
- Final top-layer paving
- Final striping, pavement marking and signs
- Paving the center of the roundabout
- Seed establishment in the shoulders
Paving and striping may require 2-3 days of road closures. Paving will be schedule during warmer, drier weather. We will post signs and send an update about two weeks before the planned closures.
Thank you for your patience and support of this project.
|